[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127590":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1127590,793,1,"单选题","（2020年真题）根据《水利工程设计变更管理暂行办法》，不需要报原初步设计审批部门审批的设计变更是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","主要建筑物形式变化",false,{"key":16,"text":17,"correct":14},"B","水库库容变化",{"key":19,"text":20,"correct":21},"C","堤防工程局部基础处理方案变化",true,{"key":23,"text":24,"correct":14},"D","主要料场场地变化","P142-144 重大设计变更文件，由项目法人按原报审程序报原初步设计审批部门审批。一般设计变更由项目法人组织审查确认后，并报项目主管部门核各，必要时报项目主管部门审批。题目中主要建筑物形式变化、水库库容变化、主要料场场地变化均属于重大设计变更;对于堤防工程局部基础处理方案变化属于一般设计变更。因此选择C选项。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]