[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127582":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1127582,793,1,"单选题","在水利工程建设程序中，不属于前期工作的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目建议书",false,{"key":16,"text":17,"correct":14},"B","可行性研究报告",{"key":19,"text":20,"correct":21},"C","招标设计",true,{"key":23,"text":24,"correct":14},"D","初步设计","根据水利部《水利工程建设项目管理规定》（水建[1995]128号）和有关规定，水利工程建设项目的实施，必须执行工程建设程序。水利工程建设程序一般分为：项目建议书、可行性研究报告、施工准备、初步设计、建设实施、生产准备、竣工验收、后评价等阶段，各阶段工作实际开展时间可以重叠。一般情况下，项目建议书、可行性研究报告、初步设计称为前期工作。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]