[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127578":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1127578,793,1,"单选题","根据《水利工程建设项目管理规定》（水建[1995]128号），水利水电工程完成建设目标的标志是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同工程完工验收",false,{"key":16,"text":17,"correct":14},"B","专项验收",{"key":19,"text":20,"correct":14},"C","后评价",{"key":22,"text":23,"correct":24},"D","竣工验收",true,"水利工程建设项目建设阶段划分，竣工验收是工程完成建设目标的标志，是全面考核建设成果、检验设计和工程质量的重要步骤。竣工验收合格的工程建设项目即可以从基本建设转人生产（运行)。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]