[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127577":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1127577,793,1,"单选题","根据《水利工程建设程序管理暂行规定》（水建[1998]16号），水利工程建设项目生产准备阶段的工作应由()完成。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目主管部门",false,{"key":16,"text":17,"correct":18},"B","项目法人",true,{"key":20,"text":21,"correct":14},"C","运行管理单位",{"key":23,"text":24,"correct":14},"D","施工单位","生产准备阶段，生产准备（运行准备）指为工程建设项目投入运行前所进行的准备工作，完成生产准备（运行准备）是工程由建设转入生产（运行）的必要条件。项目法人应按照建管结合和项目法人责任制的要求，适时做好有关生产准备（运行准备）工作。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]