[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127567":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1127567,793,1,"单选题","在龙门建造浮桥，延龙口前沿抛投块料，使堆筑戗堤均匀上升的截流方法是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","立堵法",false,{"key":16,"text":17,"correct":18},"B","平堵法",true,{"key":20,"text":21,"correct":14},"C","塞堵法",{"key":23,"text":24,"correct":14},"D","盖堵法","平堵（如图2F312021-1所示）是先在龙口建造浮桥或栈桥，由自卸汽车或其他运输工具运来抛投料，沿龙口前沿投拋。先下小料?随着流速增加?逐渐抛投大块料，使堆筑戗堤均匀地在水下上升，直至高出水面，截断河床。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]