[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127558":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1127558,793,1,"单选题","导流设计流量是指在导流时段内按导流标准选择相应洪水重现期的()流量。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","平均",false,{"key":16,"text":17,"correct":14},"B","设计",{"key":19,"text":20,"correct":14},"C","校核",{"key":22,"text":23,"correct":24},"D","最大",true,"导流标准，土坝、堆石坝、支墩坝一般不允许过水，可见当施工期较长，而洪水来临前又不能完建时，导流时段就要以全年为标准，其导流设计流量，就应按导流标准选择相应洪水重现期的年最大流量。如安排的施工进度能够保证在洪水来临前使坝身起拦洪作用，其导流时段应为洪水来临前的施工时段，导流设计流量则为该时段内按导流标准选择相应洪水重现期的最大流量。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]