[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127554":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1127554,793,1,"单选题","（2018年）下列化学灌浆施工工序中，正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","钻孔、裂缝处理、压水试验、埋设注浆嘴和回浆嘴、封闭、注水、灌浆",false,{"key":16,"text":17,"correct":14},"B","钻孔、裂缝处理、埋设注浆嘴和回浆嘴、压水试验、封闭、灌浆、注水",{"key":19,"text":20,"correct":21},"C","钻孔、压水试验、裂缝处理、埋设注浆嘴和回浆嘴、封闭、注水、灌浆",true,{"key":23,"text":24,"correct":14},"D","钻孔、压水试验、裂缝处理、埋设注浆嘴和回浆嘴、注水、灌浆、封闭","化学灌浆的工序依次是：钻孔及压水试验，钻孔及裂缝的处理（包括排渣及裂缝干燥处理），埋设注浆嘴和回浆嘴以及封闭、注水和灌浆。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]