[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127550":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1127550,793,1,"单选题","（2017年）下列关于植筋锚固施工的说法中，正确的是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工中钻出的废孔，可采用与结构混凝土同强度等级的水泥砂浆",false,{"key":16,"text":17,"correct":14},"B","植筋可以使用光圆钢筋",{"key":19,"text":20,"correct":21},"C","植入孔内部分钢筋上的锈迹、油污应打磨清除干净",true,{"key":23,"text":24,"correct":14},"D","化学锚栓如需焊接，应在固化后方可进行","考点:混凝土结构失稳。选项A，施工中钻出的废孔，应采用高于结构混凝土一个强度等级的水泥砂浆、树脂水泥砂浆或锚固胶粘剂进行填实；选项B，当植筋时，应使用热轧带肋钢筋，不得使用光圆钢筋；选项D，固化后不得进行焊接。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]