[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127534":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1127534,793,1,"单选题","某水闸启闭机房钢筋混凝土悬臂梁跨度为1.8m，其底模拆除时，混凝土的强度至少应达到设计强度等级的()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","50%",false,{"key":16,"text":17,"correct":18},"B","70%",true,{"key":20,"text":21,"correct":14},"C","80%",{"key":23,"text":24,"correct":14},"D","90%","五、模板的拆除 1.拆模时间拆模的迟早直接影响混凝土质量和模板使用的周转率。拆模时间应根据设计要求、气温和混凝土强度增长情况而定。(1)施工规范规定，非承重侧面模板，混凝土强度应达到25×105Pa以上，其表面和棱角不因拆模而损坏时方可拆除。一般情况，夏天需2~4d；冬天需5~7d；混凝土表面质量要求高的部位，拆模时间宜晚一些。(2)钢筋混凝土结构的承重模板，要求达到下列规定值按混凝土设计强度等级的百分率计算）时才能拆模：①悬臂板、梁：跨度2m；70%;跨度2m；100%。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]