[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127529":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1127529,793,1,"单选题","某水利工程受弯构件受拉区的受力钢筋为10Φ25，如受力钢筋采用焊接接头，同一截面内的钢筋接头最多只能有()个。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":21},"C","5",true,{"key":23,"text":24,"correct":14},"D","6","3.接头的分布要求钢筋接头应分散布置。配置在同一截面内的下述受力钢筋，其接头的截面面积占受力钢筋总截面面积的百分率，应符合下列规定：(1)焊接接头，在查弯构件的受拉区，不宜超过50%;受压K不受限制。(2)绑扎接头，在受弯构件的受拉区，不宜超过25%;受压区不宜超过50%。(3)机械连接接头，其接头分布应按设计规定执行，当设计没有要求时，在受拉区不宜超过.50%;在受压K或装配式构件中钢筋受力较小部位.A级接头不受限制。(4)焊接与绑扎接头距离钢筋弯头起点不得小于10d?也不应位于最大弯矩处。(5)若两根相邻的钢筋接头中距在500mm以内或两绑扎接头的中距在绑扎搭接长度以内，均作为同一截面处理。10×50%=5根",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]