[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127525":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1127525,793,1,"单选题","根据水工混凝土施工规范的相关规定，混凝土非承重侧面模板拆除时，混凝土强度至少应达到()×10Pa。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":18},"B","25",true,{"key":20,"text":21,"correct":14},"C","30",{"key":23,"text":24,"correct":14},"D","35","拆模时间，(1)施工规范规定，非承重侧面模板，混凝土强度应达到25X105Pa以上，其表面和棱角不因拆模而损坏时方可拆除。一般情况，夏天需2~4d，冬天需5~7d。混凝土表面质量要求高的部位，拆模时间宜晚一些。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]