[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127515":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1127515,793,1,"单选题","水利水电工程土基开挖施工中，当开挖临近设计高程时，应预留厚度为()m的保护层，待上部结构施工时再人工挖除。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.1～0.2",false,{"key":16,"text":17,"correct":18},"B","0.2～0.3",true,{"key":20,"text":21,"correct":14},"C","0.3～0.5",{"key":23,"text":24,"correct":14},"D","0.5～0.7","混凝土外加剂的使用，1.土基开挖与清理(1)坝断面范围内必须清除地基、岸坡上的草皮、树根、含有植物的表土、蛮石、垃圾及其他废料，并将清理后的地基表面土层压实。(2)坝体断面范围内的低强度、高压缩性软土及地震时易液化的土层应清除或处理。(3)开挖的岸坡应大致平顺，不应成台阶状、反坡或突然变坡，岸坡上缓下陡时，变坡角应小于20°，岸坡不宜陡于1:1.5。(4)应留有0.2~0.3m的保护层，待填土前进行人工开挖。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]