[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127505":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1127505,793,1,"单选题","（2019年）混凝土重力坝排水廊道一般布置在（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","坝基础位置",false,{"key":16,"text":17,"correct":18},"B","坝上游侧",true,{"key":20,"text":21,"correct":14},"C","坝中心线位置",{"key":23,"text":24,"correct":14},"D","坝下游侧","为了便于检查坝体和排除坝体渗水，在靠近坝体上游面沿高度每隔15-30m设一检查兼作排水作用的廊道。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]