[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127495":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1127495,793,1,"单选题","根据《水利水电工程等级划分及洪水标准》（SI252—2000），拦河水闸工程等级别的确定依据是（）过闸流量。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最大",true,{"key":16,"text":17,"correct":18},"B","设计",false,{"key":20,"text":21,"correct":18},"C","平均",{"key":23,"text":24,"correct":18},"D","最小","拦河水闸工程的等别，应根据其最大过闸流量，按表2F311011-2确定。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]