[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127465":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1127465,793,1,"单选题","（2017年）土坝施工放样时，在施工范围内布设直接用于坝体高程放样的临时水准点，最低可按（ ）精确施测。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","等外",true,{"key":16,"text":17,"correct":18},"B","四等",false,{"key":20,"text":21,"correct":18},"C","三等",{"key":23,"text":24,"correct":18},"D","二等","考点:土坝的施工放样。临时水准点应根据施工进度及时设置，并与永久水准点构成附合或闭合水准路线，按等外精度施测，并要根据永久水准点定期进行检测。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]