[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127466":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127466,792,2,"多选题","成本分析的方法有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","动态控制法",false,{"key":16,"text":17,"correct":18},"B","因素分析法",true,{"key":20,"text":21,"correct":18},"C","差额计算法",{"key":23,"text":24,"correct":18},"D","比较法",{"key":26,"text":27,"correct":18},"E","比率法","BCDE","2020版教材P224 本题主要考察的是：项目施工成本分析。见原文：由于工程成本涉及的范围很广，需要分析的内容很多，应该在不同的情况下，采取不同的分析方法。应该在不同的情况下，采取不同的分析方法。常用的分析方法有比较法、因素分析法、差额计算法和比率法。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]