[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127463":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127463,792,2,"多选题","项目施工成本目标控制的原则包括（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","成本最低化",true,{"key":16,"text":17,"correct":14},"B","全员成本管理",{"key":19,"text":20,"correct":21},"C","分层统一",false,{"key":23,"text":24,"correct":14},"D","动态控制",{"key":26,"text":27,"correct":14},"E","责权利相结合","ABDE","2020版教材P220 2019版教材P223~224页 本题的考点为项目施工成本目标控制的原则。施工项目经理部在对项目施工目标成本控制时，必须遵循以下基本原则：（1）成本最低原则；（2）全员成本管理原则；（3）目标分解原则；（4）动态控制原则；（5）责、权、利相结合原则。分层统一是施工成本管理机构的设置要求，因此，选项C是干扰项。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]