[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127456":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127456,792,2,"多选题","关于施工成本分析任务的说法，正确的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","找出产生差异的原因",true,{"key":16,"text":17,"correct":14},"B","提出进一步降低成本的措施和方案",{"key":19,"text":20,"correct":21},"C","对尚未或正在发生的经济活动进行核算",false,{"key":23,"text":24,"correct":14},"D","对成本计划的执行情况进行正确评价",{"key":26,"text":27,"correct":14},"E","正确计算成本计划的执行结果，计算产生的差异","ABDE","2020版教材P223 施工成本分析的任务包括：1、正确计算成本计划的执行结果，计算产生的差异；2、找出产生差异的原因；3、对成本计划的执行情况进行正确评价；4、提出进一步降低成本的措施和方案。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]