[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127452":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127452,792,2,"多选题","从合同风险的来源性质分，有()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","政治风险",true,{"key":16,"text":17,"correct":14},"B","经济风险",{"key":19,"text":20,"correct":14},"C","技术风险",{"key":22,"text":23,"correct":14},"D","公共关系风险",{"key":25,"text":26,"correct":27},"E","项目风险",false,"ABCD","2020版教材P217 合同风险因素的分类。 (1)按风险严峻程度分为特殊风险（非常风险）和其他风险。 (2)按工程实施不同阶段分为投标阶段风险、合同谈判阶段风险、合同实施阶段风险。 (3)按风险的范围分为项目风险、国别风险和地区风险。 (4)从风险的来源性质可分为政治风险、经济风险、技术风险、商务风险、公共关系风险和管理风险等。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]