[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127449":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127449,792,2,"多选题","索赔过程中的28d时效规定，适用于索赔程序中的()过程。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","承包人提出索赔申请",true,{"key":16,"text":17,"correct":14},"B","承包人提出索赔报告和相关证据资料",{"key":19,"text":20,"correct":14},"C","监理工程师和业主审核承包人的索赔申请",{"key":22,"text":23,"correct":14},"D","索赔事件终了承包人提供最终索赔报告",{"key":25,"text":26,"correct":27},"E","发包人审批监理工程师的索赔处理证明",false,"ABCD","2020版教材P215 (1) 根据招标文件及合同要求的有关规定提出索赔意向书，合同实施过程中，凡不属于承包方责任导致项目拖延和成本增加事件发生后的28d内，必须以正式函件通知监理工程师，声明对此事件要求索赔。(2) 正式提出索赔申请后，承包方应抓紧准备索赔的证据资料。(3) 监理工程师在收到承包方送交的索赔报告和有关资料后，于28d 内给予答复，或要求承包方进一步补充索赔理由和证据。监理工程师在28d内未予答复或未对承包方作进一步要求，视为该项索赔已经认可。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]