[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127448":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127448,792,2,"多选题","施工索赔引起的原因可能有()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","延期发出图纸产生的索赔",true,{"key":16,"text":17,"correct":14},"B","恶劣的气候条件导致的索赔",{"key":19,"text":20,"correct":14},"C","工程变更导致的索赔",{"key":22,"text":23,"correct":14},"D","由外部环境而引起的索赔",{"key":25,"text":26,"correct":27},"E","项目部人员调整",false,"ABCD","2020版教材P215 市政公用工程项目施工管理中的索赔。索赔项目概述：1.延期发出图纸产生的索赔；2.恶劣的气候条件导致的索赔；3.工程变更导致的索赔；4.以承包方能力不可预见引起的索赔；5.由外部环境而引起的索赔；6.监理工程师指令导致的索赔；7.其他原因导致的承包方的索赔。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]