[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127444":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127444,792,2,"多选题","施工过程中承包方的索赔要求最终归结为()索赔。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工期",true,{"key":16,"text":17,"correct":18},"B","工程量",false,{"key":20,"text":21,"correct":14},"C","费用",{"key":23,"text":24,"correct":18},"D","拆迁拖延",{"key":26,"text":27,"correct":18},"E","材料涨价幅度超过合同约定","AC","2020版教材P215 市政公用工程项目施工管理中的索赔。施工过程中主要是工期索赔和费用索赔。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]