[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127442":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127442,792,2,"多选题","关于施工过程中的合同变更，正确的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","标高、基线、尺寸变更",true,{"key":16,"text":17,"correct":14},"B","工程量增减",{"key":19,"text":20,"correct":21},"C","施工机械内部调整",false,{"key":23,"text":24,"correct":14},"D","质量及特性变更",{"key":26,"text":27,"correct":14},"E","施工顺序变化","ABDE","2020版教材P214 施工过程中遇到的合同变更，如工程量增减，质量及特性变更，高程、基线、尺寸等变更。施工顺序变化。永久工程附加工作、设备、材料和服务的变更等",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]