[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127435":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127435,792,2,"多选题","在工程实施阶段现场确认实际工程数量时应重点关注的是（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","项目具体实施工艺与原招标清单特征描述的差异",true,{"key":16,"text":17,"correct":14},"B","原招标图与施工图之间的工程量差异",{"key":19,"text":20,"correct":14},"C","工程内容特征的差异",{"key":22,"text":23,"correct":14},"D","原招标现场与实施现场的差异",{"key":25,"text":26,"correct":27},"E","找出招标人提供的工程量清单中的漏洞",false,"ABCD","2020版教材P212-213 工程实施阶段：根据计价规范中的工程量计算规则，结合投标时的综合单价和经过现场工程师确认的实际工程数量，构成工程进度款的支付额度。 该阶段重点关注的是对施工方有利的项目具体实施工艺与原招标清单特征描述的差异;原招标图与施工图之间的工程量差异、工程内容特征的差异;原招标现场与实施现场的差异等并做好有效的原始记录。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]