[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127410":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127410,792,2,"多选题","下列给水排水管道工程施工质量控制应符合的规定，符合规范的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","各分项工程应按照施工技术标准进行质量控制",true,{"key":16,"text":17,"correct":18},"B","每分项工程完成后，应进行检验",false,{"key":20,"text":21,"correct":14},"C","相关各分项工程之间，必须进行交接检验",{"key":23,"text":24,"correct":14},"D","所有隐蔽分项工程必须进行隐蔽验收",{"key":26,"text":27,"correct":14},"E","未经检验或验收不合格不得进行下道分项工程","ACDE","2020版教材P338 根据《给水排水管道施工及验收规范》GB50268-2008第3.1.15条，规定：1）各分项工程应按照施工技术标准进行质量控制，每分项工程完成后，必须进行检验2）相关各分项工程之间，必须进行交接检验，所有隐蔽分项工程必须进行隐蔽验收，未经检验或验收不合格不得进行后序分项工程。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]