[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127379":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127379,792,2,"多选题","开工前应根据( )编制工程测量方案。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工方案",true,{"key":16,"text":17,"correct":14},"B","建（构）筑物特点",{"key":19,"text":20,"correct":21},"C","仪器设备",false,{"key":23,"text":24,"correct":14},"D","设计要求的施测精度",{"key":26,"text":27,"correct":21},"E","测量控制网点","ABD","2021\u002F2020版教材P192页 根据施工方案和场区构筑物特点及设计要求的施测精度，编制工程测量方案。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]