[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127309":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127309,792,2,"多选题","沥青混合料面层的施工工序包括（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","摊铺",true,{"key":16,"text":17,"correct":14},"B","压实",{"key":19,"text":20,"correct":14},"C","接缝处理",{"key":22,"text":23,"correct":24},"D","沥青材料选择",false,{"key":26,"text":27,"correct":14},"E","开放交通","ABCE","2021\u002F2020版教材P19 沥青混合料面层施工技术包括：一.施工准备；二.摊铺作业；三.压实成型与接缝；四.开放交通。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]