[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127297":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127297,792,2,"多选题","下列关于级配碎石（碎砾石）基层施工技术要求，正确的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","运输中应采取防止水分蒸发和防扬尘措施",true,{"key":16,"text":17,"correct":14},"B","宜采用机械摊铺，摊铺应均匀一致，发生“梅花”、“砂窝”现象应及时翻拌均匀",{"key":19,"text":20,"correct":21},"C","宜用多次找补方式达到每层的虚铺厚度要求",false,{"key":23,"text":24,"correct":14},"D","碾压前和碾压中应先适量洒水",{"key":26,"text":27,"correct":14},"E","可采用沥青乳液和沥青下封层进行养护，养护期为7～14d","ABDE","2021\u002F2020版教材P17页 级配碎石级配砾石基层材料的压实系数均应通过实验确定，每层应虚铺厚度一次铺齐，颗粒分布均匀，厚度一致，不得多次找补，所以C项错误。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]