[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127280":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127280,792,2,"多选题","关于石方路基施工的说法，正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","应先清理地表，再开始填筑施工",true,{"key":16,"text":17,"correct":18},"B","先填筑石料，再码砌边坡",false,{"key":20,"text":21,"correct":18},"C","宜用12t以下振动压路机",{"key":23,"text":24,"correct":18},"D","路基范围内管线四周宜回填石料",{"key":26,"text":27,"correct":14},"E","碾压前应经过试验段，确定施工参数","AE","2021\u002F2020版教材P11页 石方路基施工技术要求1.修筑填石路堤应进行地表清理，先码砌边部，然后逐层水平填筑石料，确保边坡稳定。2.先修筑试验段，以确定松铺厚度、压实机具组合、压实遍数及沉降差等施工参数。3.填石路堤宜选用12t以上的振动压路机、25t以上轮胎压路机或2.5t的夯锤压（夯）实。4.路基范围内管线、构筑物四周的沟槽宜回填土料。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]