[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127258":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127258,792,2,"多选题","下列 HDPE渗沥液收集花管施工控制要点中，正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","HDPE 管的直径:干管不应小于250mm,支管不应小于200mm。",true,{"key":16,"text":17,"correct":18},"B","HDPE管的布置宜呈直线，其连接处应密封",false,{"key":20,"text":21,"correct":14},"C","管材或管件连接面上的污物应用洁净棉布擦净",{"key":23,"text":24,"correct":14},"D","应铣削连接面，使其与轴线垂直，并使其与对应的断面吻合",{"key":26,"text":27,"correct":14},"E","热熔连接保压、冷却时间，应符合热熔连接工具生产厂和管件、管材生产厂规定","ACDE","2021\u002F2020版教材P185 四、施工控制要点,(3) HDPE管的直径：干管不应小于250mm, 支管不应小于200mmHDPE管的开孔率应保证强度要求。HDPE管的布置宜呈直线，其转弯角度应小于或等于20。，其连接处 不应密封。 (4) 管材或管件连接面上的污物应用洁净棉布擦净，应铣削连接面，使其与轴线垂 直，并使其与对应的断面吻合。 (6) 热溶连接保压、冷却时间，应符合热熔连接工具生产厂和管件、管材生产厂规 定，并保证冷却期间不得移动连接件或在连接件上施加外力。 ( 7 ) 设定工人行走路线，防止反复踩踏HDPE土工膜。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]