[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127255":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127255,792,2,"多选题","关于生活垃圾卫生填埋场HDPE膜的施工要求，正确的有( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","铺设应一次展开到位",true,{"key":16,"text":17,"correct":14},"B","应为膜尺寸变化留出伸缩量",{"key":19,"text":20,"correct":14},"C","应对膜下保护层采取防、排水措施",{"key":22,"text":23,"correct":14},"D","应防止膜受风力影响破坏",{"key":25,"text":26,"correct":27},"E","膜应全部展开后统一焊接",false,"ABCD","2021\u002F2020版教材P179 生活垃圾卫生填埋场HDPE膜的施工要求。根据《生活垃圾卫生填埋场防渗系统工程技术规范》CJJ113-2007第5.3.5条的规定：HDPE膜铺设时应符合下列要求：(1)铺设应一次展开到位，不宜展开后再拖动；(2)应为材料热胀冷缩导致的尺寸变化留出伸缩量；(3)应对膜下保护层采取适当的防水、排水措施；(4)应采取措施防止HDPE膜受风力影响而破坏。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]