[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127238":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127238,792,2,"多选题","有关城镇供热管道试运行要求，说法错误的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","应缓慢地升温，升温速度不应大于10℃\u002Fh",false,{"key":16,"text":17,"correct":18},"B","试运行应连续运行48h以上",true,{"key":20,"text":21,"correct":14},"C","供热管线工程应与换热站工程联合进行试运行",{"key":23,"text":24,"correct":18},"D","在试运行期间，管道法兰处的螺栓应进行热拧紧，热拧紧时的运行压力应降低至0.5MPa以下",{"key":26,"text":27,"correct":14},"E","供热管道试运行应在设计的参数下运行","BD","P159-161 1)供热管线工程应与换热站工程联合进行试运行。 2) 试运行应有完善可靠的通信系统及安全保障措施。 3)试运行应在设计的参数下运行。试运行时间应为达到试运行的参数条件下连续运行72h。试运行应缓慢升温，升温速度不得大于10℃\u002Fh。在低温试运行期间，应对管道、设备进行全面检查，支架的工作状况应做重点检查。在低温试运行正常以后，方可缓慢升温至试运行温度下运行。 4)在试运行期间，管道法兰、阀门、补偿器及仪表等处的螺栓应进行热拧紧。热拧紧时的运行压力应降低至0.3MPa以下。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]