[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127220":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127220,792,2,"多选题","采用成品管新建市政管道工程常用的不开槽施工方法有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","顶管法",true,{"key":16,"text":17,"correct":14},"B","夯管法",{"key":19,"text":20,"correct":21},"C","裂管法",false,{"key":23,"text":24,"correct":21},"D","沉管法",{"key":26,"text":27,"correct":21},"E","盾构法","AB","P135-137 本题涉及的考点为市政管道工程常用的不开槽施工方法。 市政公用工程常用的不开槽管道施工方法有顶管（含曲线）法、盾构法、浅埋暗挖法、水平定向钻法、夯管法等。 本题的题干加了限制词“采用成品管”、“新建”，就将C、E选项排除在外。 盾构法采用的是管片；裂管法是旧管道修复方法；沉管法是大型隧道的施工方法，需要在大江、大海底部挖槽。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]