[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127219":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127219,792,2,"多选题","关于沟槽开挖与支护说法错误的是()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","撑板支撑应随挖土及时安装",false,{"key":16,"text":17,"correct":14},"B","人工开挖沟槽的槽深超过3m时应分层开挖，每层深度不超过2m",{"key":19,"text":20,"correct":14},"C","人工开挖多层沟槽的层间留台宽度直槽时不应小于0．5m",{"key":22,"text":23,"correct":24},"D","机械开挖至槽底",true,{"key":26,"text":27,"correct":24},"E","为降低成本，施工人员可由支撑上下沟槽","DE","P132-135 D选项的正确表述：槽地基土不得扰动，机械开挖时槽底预留200～300mm土层，由人工开挖至设计标高，整平。 E选项的正确表述：施工人员应由安全梯上下沟槽，不得攀登支撑。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]