[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127168":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127168,792,2,"多选题","压力管道试验准备工作包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","试验管段所有敞口应封闭，不得有渗漏水现象",true,{"key":16,"text":17,"correct":14},"B","试验管段不得用闸阀做堵板，不得含有消火栓、水锤消除器、安全阀等附件",{"key":19,"text":20,"correct":14},"C","水压试验前应清除管道内的杂物",{"key":22,"text":23,"correct":14},"D","应做好水源引接、排水等疏导方案",{"key":25,"text":26,"correct":27},"E","管道已回填土",false,"ABCD","2021\u002F2020版教材P140 城市管道工程中压力管道的实验准备工作：1）试验管段所有敞口应封闭，不得有渗漏水现象2）试验管段不得用闸阀做堵板，不得含有消火栓、水锤消除器、安全阀等附件3）水压试验前应清除管道内的杂物4）应做好水源引接、排水等疏导方案.",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]