[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127156":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127156,792,2,"多选题","给水排水管道采用开槽施工时，沟槽开挖的规定有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","机械开挖时槽底预留200～300㎜土层，由人工开挖至设计高程，整平",true,{"key":16,"text":17,"correct":14},"B","槽底不得受水浸泡或受冻，槽底局部扰动或受水浸泡时，宜采用天然级配砂砾石或石灰土回填",{"key":19,"text":20,"correct":21},"C","槽底土层为杂填土、腐蚀性土时，应用振动碾碾压夯实",false,{"key":23,"text":24,"correct":14},"D","槽底扰动土层为湿陷性黄土时，应按设计要求进行地基处理",{"key":26,"text":27,"correct":14},"E","槽底原状地基土不得扰动","ABDE","2021\u002F2020版教材P134 沟槽开挖规定：(1)槽底原状地基土不得扰动，机械开挖时槽底预留200-300mm土层，由人工开挖至设计高程，整平,。(2)槽底不得受水浸泡或受冻，槽底局部扰动或受水浸泡时，宜采用天然级配砂砾石或石灰土回填；槽底扰动土层为湿陷性黄土时应按设计要求进行地基处理。(3)槽底土层为杂填土、腐蚀性土时，应全部挖除并按设计要求进行地基处理。(4)槽壁平顺，边坡坡度符合施工方案的规定。(5)在沟槽边坡稳固后设置供施工人员上下沟槽的安全梯。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]