[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127153":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127153,792,2,"多选题","下列水池(构筑物)工程施工时，应采取降排水措施的有（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","受地表水、地下动水压力作用影响的地下结构工程",true,{"key":16,"text":17,"correct":14},"B","采用排水法下沉和封底的沉井工程",{"key":19,"text":20,"correct":14},"C","坑底至承压含水层顶板之间的土体重力不能平衡承压水水头的水池基坑工程",{"key":22,"text":23,"correct":24},"D","施作完抗浮结构的水池",false,{"key":26,"text":27,"correct":24},"E","正进行水下封底的沉井","ABC","P130-131 下列水池(构筑物)工程施工应采取降（排）水措施： (1)受地表水、地下动水压力作用影响的地下结构工程。 (2)采用排水法下沉和封底的沉井工程。 (3)基坑底部存在承压含水层,且经验算基底开挖面至承压含水层顶板之间的土体重力不足以平衡承压水水头压力,需要减压降水的工程。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]