[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127145":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127145,792,2,"多选题","水池满水试验的做法包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","设计预留孔洞、预埋管口及进出水口等已做临时封堵并达到强度要求",true,{"key":16,"text":17,"correct":14},"B","向池内注水宜分3次进行，每次注水高度为设计水深的1\u002F3",{"key":19,"text":20,"correct":14},"C","相邻两次注水的间隔时间不应小于24h",{"key":22,"text":23,"correct":14},"D","注水时水位上升速度不宜超过2m\u002Fd",{"key":25,"text":26,"correct":27},"E","注水至设计水位12h后，开始测读水位测针的初读数",false,"ABCD","2021\u002F2020版教材P132 2K314024构筑物满水试验的规定 (3)设计预留孔洞、预埋管口及进出水口等已做临时封堵，且经验算能安全承受试验 压力。 (1)向池内注水宜分3次进行，每次注水为设计水深的1\u002F3。 (2)注水时水位上升速度不宜超过2m\u002Fd。 相邻两次注水的间隔时间不应小于24h。 (3)注水至设计水深24h后，开始测度水位测针的初读数。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]