[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127137":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127137,792,2,"多选题","分节制作沉井时，应做到( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","第一节制作高度必须高于刃脚部分",true,{"key":16,"text":17,"correct":14},"B","沉井内设有底梁或支撑梁时应与刃脚部分整体浇捣",{"key":19,"text":20,"correct":14},"C","设计无要求时，混凝土强度应达到设计强度等级75%后，方可拆除模板或浇筑后节混凝土",{"key":22,"text":23,"correct":24},"D","混凝土施工缝处理应采用凹凸缝或设置橡胶止水带",false,{"key":26,"text":27,"correct":14},"E","内外模板采用对拉螺栓固定时，其对拉螺栓的中间应设置防渗止水片","ABCE","2021\u002F2020版教材P128 分节制作沉井的要求如下：1)每节制作高度应符合施工方案要求，且第一节制作高度必须高于刃脚部分；井内设有底梁或支撑梁时应与刃脚部分整体浇捣。2)设计无要求时，混凝土强度应达到设计强度等级的75%后，方可拆除模板或浇筑后节混凝土。3)混凝土施工缝处理应采用凹凸缝或设置钢板止水带。内外模板采用对拉螺栓固定时，其对拉螺栓的中间应设置防渗止水片。此处施工缝为刚性连接，所以要做成凹凸缝或设置钢板止水带。橡胶止水带是弹性缝，一般用于结构的变形缝、沉降缝处。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]