[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127134":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127134,792,2,"多选题","关于分节制作沉井的要求，正确的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","第一节制作高度必须高于刃脚部分",true,{"key":16,"text":17,"correct":14},"B","设计无要求时，前节混凝土强度应达到设计强度75%，方可浇筑后节混凝土",{"key":19,"text":20,"correct":21},"C","沉井每次接高时各部位的轴线位置应基本重合",false,{"key":23,"text":24,"correct":14},"D","混凝土施工缝处理应采用凹凸缝或设置钢板止水带，施工缝应凿毛并清理干净",{"key":26,"text":27,"correct":14},"E","分节制作、分次下沉的沉井严禁在接高施工过程中发生倾斜和突然下沉","ABDE","2021\u002F2020版教材P128 (1）每节制作高度应符合施工方案要求，且第一节制作高度必须高于刃脚部分；井内设有底梁或支撑梁时应与刃脚部分整体浇捣。（2）设计无要求时，混凝土强度应达到设计强度等级75%后，方可拆除模板或浇筑后一节混凝土。（3）混凝土施工缝处理应采用凹凸缝或设置钢板止水带，施工缝应凿毛并清理干净;内外模板采用对拉螺栓固定时，其对拉螺栓的中间应设置防渗止水片；钢筋密集部位和预留孔底部应辅以人工振捣，保证结构密实。（4）沉井每次接髙时各部位的轴线位置应一致、重合，及时做好沉降和位移监测；必要时应对刃脚地基承载力进行验算，并采取相应措施确保地基及结构的稳定。(5)分节制作、分次下沉的沉井，前次下沉后进行后续接高施工。1）应验算接高后稳定系数等，并应及时检查沉井的沉降变化情况，严禁在接髙施工过程中沉井发生倾斜和突然下沉；",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]