[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127129":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127129,792,2,"多选题","给水与污水处理设备正式运行前必须进行联机试运行，具体要求包括( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","按工艺流程各构筑物逐个通水联机试运行正常",true,{"key":16,"text":17,"correct":14},"B","全厂联机试运行、协联运行正常",{"key":19,"text":20,"correct":14},"C","先采用手工操作，处理构筑物和设备全部运转正常后，方可转入自动控制运行",{"key":22,"text":23,"correct":24},"D","全厂联机运行应不少于48h",false,{"key":26,"text":27,"correct":14},"E","监测并记录各构筑物运行情况和运行数据","ABCE","2021\u002F2020版教材P123页 联机运行要求1）按工艺流程在各构筑物逐个进行的通水联机试运行正常2）全厂联机试运行、协联运行正常3）先采用手工操作，处理构筑物和设备全部运行正常后。方可转入自动控制运行4）全厂联机运行应不少于24h 5）监测并记录各构筑物运行情况和运行数据。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]