[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127085":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127085,792,2,"多选题","当开挖作业面围岩自稳时间不够时，应采用（）等辅助技术对其进行加固。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","超前锚杆",true,{"key":16,"text":17,"correct":18},"B","喷射混凝土封闭开挖工作面",false,{"key":20,"text":21,"correct":14},"C","小导管周边注浆",{"key":23,"text":24,"correct":14},"D","设置临时仰拱",{"key":26,"text":27,"correct":18},"E","钢拱架喷射混凝土","ACD","P108-112 支护与加固技术措施： 1.暗挖隧道内常用的技术措施： (1)超前锚杆或超前小导管支护。 (2)小导管周边注浆或围岩深孔注浆。 (3)设置临时仰拱。 (4)管棚超前支护。 2.暗挖隧道外常用的技术措施： (1)地表锚杆或地表注浆加固。 (2)冻结法固结地层。 (3)降低地下水位法。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]