[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127079":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127079,792,2,"多选题","环形开挖预留核心土法的施工作业有（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","开挖环形拱部",true,{"key":16,"text":17,"correct":14},"B","架立钢支撑、挂钢筋网、喷混凝土",{"key":19,"text":20,"correct":14},"C","开挖核心土和下台阶，随时接长钢支撑和喷混凝土、封底",{"key":22,"text":23,"correct":24},"D","整平初次支护",false,{"key":26,"text":27,"correct":14},"E","二次衬砌作业","ABCE","P104-108 环形开挖预留核心土法施工作业流程：用人工或单臂掘进机开挖环形拱部→架立钢支撑→挂钢筋网→喷混凝土。在拱部初次支护保护下，为加快进度，宜采用挖掘机或单臂掘进机开挖核心土和下台阶，随时接长钢支撑和喷射混凝土、封底。视初次支护的变形情况或施工步序，安排施工二次衬砌作业。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]