[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127046":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127046,792,2,"多选题","双侧壁导坑法的施工要点有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","将断面分成：左、右侧壁导坑、上部核心土、下台阶",true,{"key":16,"text":17,"correct":14},"B","导坑宽度不宜超过断面最大跨度的1\u002F3",{"key":19,"text":20,"correct":21},"C","开挖流水顺序为左侧壁导坑、上部核心土、右侧壁导坑、下台阶",false,{"key":23,"text":24,"correct":14},"D","后开挖导坑所引起的围岩应力重分布的影响不应波及另一侧已成导坑",{"key":26,"text":27,"correct":14},"E","每个分块开挖后必须立即闭合各自的初次支护","ABDE","2021\u002F2020版教材P106页 双侧壁导坑法:双侧壁导坑法一般是将断面分成四块：左、右侧壁导坑、上部核心土、下台阶。导坑尺寸拟定的原则同前，但宽度不宜超过断面最大跨度的1\u002F3。左、右侧导坑错开的距离，应根据开挖一侧导坑所引起的围岩应力重分布的影响不致波及另一侧已成导坑的原则确定。开挖一侧导坑，并及时地将其初次支护闭合。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]