[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127045":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127045,792,2,"多选题","以下关于双侧壁导坑法施工工艺说法正确的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","先开挖一侧导坑，并及时地将其初次支护闭合",true,{"key":16,"text":17,"correct":18},"B","同时开挖另一侧导坑，并建造初次支护",false,{"key":20,"text":21,"correct":14},"C","然后开挖上部核心土，建造拱部初次支护",{"key":23,"text":24,"correct":14},"D","再后开挖下台阶，建造底部的初次支护，使初次支护全断面闭合",{"key":26,"text":27,"correct":14},"E","最后拆除导坑临空部分的初次支护，施作内层衬砌","ACDE","2021\u002F2020版教材P106页 施工顺序：开挖一侧导坑，并及时地将其初次支护闭合→相隔适当距离后开挖另一侧导坑，并建造初次支护→开挖上部核心土，建造拱部初次支护，拱脚支承在两侧壁导坑的初次支护上→开挖下台阶，建造底部的初次支护，使初次支护全断面闭合→拆除导坑临空部分的初次支护→施作内层衬砌。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]