[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127002":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1127002,792,2,"多选题","基坑开挖过程中应立即停止挖土的异常情况是( )等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","边坡出现失稳征兆时",true,{"key":16,"text":17,"correct":18},"B","开挖暴露出的基底受到扰动",false,{"key":20,"text":21,"correct":14},"C","开挖暴露出的基底出现明显异常（包括黏性土时强度明显偏低或砂性土层时水位过高造成开挖施工困难时）",{"key":23,"text":24,"correct":14},"D","围护结构或止水帷幕出现渗漏，或基坑出现流土、管涌现象",{"key":26,"text":27,"correct":14},"E","支护结构变形达到设计规定的控制值或变形速率持续增长且不收敛","ACDE","2021\u002F2020版教材P100页 发生下列异常情况时，应立即停止开挖，并应立即查清原因和及时采取措施后，方可继续施工： (1）支护结构变形达到设计规定的控制值或变形速率持续增长且不收敛。 (2）支护结构的内力超过其设计值或突然增大。 (3）围护结构或止水帷幕出现渗漏，或基坑出现流土、管涌现象。 (4）开挖暴露出的基底出现明显异常（包括黏性土时强度明显偏低或砂性土层时水位过高造成开挖施工困难时）。 (5）围护结构发生异常声响。 (6）边坡出现失稳征兆时。 (7）基坑周边建（构）筑物等变形过大或已经开裂",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]