[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126998":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126998,792,2,"多选题","采用浅埋暗挖法开挖作业时，其总原则是( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","预支护、预加固一段，开挖一段",true,{"key":16,"text":17,"correct":14},"B","开挖一段，支护一段",{"key":19,"text":20,"correct":21},"C","支护一段，开挖一段",false,{"key":23,"text":24,"correct":21},"D","封闭成环一段，支护一段",{"key":26,"text":27,"correct":14},"E","支护一段，封闭成环一段","ABE","2021\u002F2020版教材P77页 采用浅埋暗挖法开挖作业时，其总原则是预支护、预加固一段，开挖一段，开挖一段、支护一段，支护一段、封闭成环一段。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]