[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126987":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126987,792,2,"多选题","箱涵顶进的施工内容包括（）等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","管底土层夯压密实",false,{"key":16,"text":17,"correct":18},"B","工程降水",true,{"key":20,"text":21,"correct":18},"C","拆除加固设施",{"key":23,"text":24,"correct":18},"D","铺设润滑隔离层",{"key":26,"text":27,"correct":18},"E","拆除后背及顶进设备","BCDE","P68-70 箱涵顶进工艺流程：现场调查→工程降水→工作坑开挖→后背制作→滑板制作→铺设润滑隔离层→箱涵制作→顶进设备安装→既有线加固→箱涵试顶进→吃土顶进→监控量测→箱体就位→拆除加固设施→拆除后背及顶进设备→工作坑恢复。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]