[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126986":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126986,792,2,"多选题","关于移动模架法现浇预应力混凝土连续梁的要求，正确的有（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","模架长度必须满足施工要求",true,{"key":16,"text":17,"correct":14},"B","模架应利用专用设备组装，在施工时能确保质量和安全",{"key":19,"text":20,"correct":14},"C","内、外模板就位时，其平面尺寸、高程、预拱度的误差必须控制在容许范围内",{"key":22,"text":23,"correct":14},"D","预应力筋管道、钢筋、预埋件设置应符合规范规定和设计要求",{"key":25,"text":26,"correct":27},"E","浇筑分段工作缝，不能设在弯矩零点附近",false,"ABCD","P65-67 移动模架上浇筑预应力混凝土连续梁： (1)模架长度必须满足施工要求。 (2 )模架应利用专用设备组装，在施工时能确保质量和安全。 (3)浇筑分段工作缝,必须设在弯矩零点附近。 (4)箱梁内、外模板在滑动就位时,模板平面尺寸、高程、预拱度的误差必须控制在容许范围内。 (5)混凝土内预应力筋管道、钢筋、预埋件设置应符合规范规定和设计要求",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]