[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126983":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126983,792,2,"多选题","关于柱式墩台施工要求，正确的有（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","墩台柱与承台基础接触面应凿毛处理，清除钢筋污锈",true,{"key":16,"text":17,"correct":14},"B","浇筑墩台柱混凝土时，应铺同配合比的水泥砂浆一层",{"key":19,"text":20,"correct":14},"C","柱身高度内有系梁连接时，系梁应与柱同步浇筑",{"key":22,"text":23,"correct":14},"D","V形墩柱混凝土应对称浇筑",{"key":25,"text":26,"correct":27},"E","分层浇筑时，接缝应按施工缝处理",false,"ABCD","P60-62 柱式墩台施工： (1)模板、支架除应满足强度、刚度要求外，稳定计算中应考虑风力影响。 (2)墩台柱与承台基础接触面应凿毛处理，清除钢筋污锈。浇筑墩台柱混凝土时，应铺同配合比的水泥砂浆一层。墩台柱的混凝土宜一次连续浇筑完成。故E选项错误 (3)柱身高度内有系梁连接时，系梁应与柱同步浇筑。V形墩柱混凝土应对称浇筑。 (4)采用预制混凝土管做柱身外模时，预制管安装应符合下列要求： 1)基础面宜采用凹槽接头，凹槽深度不得小于50mm。 2)上下管节安装就位后，应采用四根竖方木对称设置在管柱四周并绑扎牢固，防止撞击错位。 3)混凝土管柱外模应设斜撑，保证浇筑时的稳定。 4)管节接缝应采用水泥砂浆等材料密封 。 (5)钢管混凝土墩柱应采用补偿收缩混凝土，一次连续浇筑完成。钢管的焊制与防腐应符合设计要求或相关规范规定。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]